Sprint 3

· 3 min read

From: 2024-10-28

To: 2024-11-11

Scrum Master: Joaquim Rosa

Product Owner: Alexandre Cotorobai

Developers: Miguel Belchior, André Oliveira, Hugo Correia

Sprint Goal

In order to complete the second milestone of our project, it is expectable to conclude the following sprints goals:

  • Access Ticket Information
  • Admin Login and Registration
  • List Purchased Tickets - Admin
  • Create Tickets - Admin
  • Deploy the project using Terraform
ExpectedQuantity
Tasks4
Epics2
Story Points12

Sprint Backlog

Tasks (SCRUM-*)DescriptionDeveloperState
SCRUM-24Access Ticket InformationNoneTODO
SCRUM-49Admin Login and RegistrationNoneTODO
SCRUM-48List Purchased Tickets - AdminNoneTODO
SCRUM-46Create Tickets - AdminNoneTODO

Task Status (Completed/Not Completed)

  • [] SCRUM-24: Access Ticket Information
  • [] SCRUM-49: Admin Login and Registration
  • [] SCRUM-48: List Purchased Tickets - Admin
  • [] SCRUM-46: Create Tickets - Admin

User Stories

User StoriesDescriptionDeveloperStateStory Points
SCRUM-24Access Ticket InformationNoneTODO3
SCRUM-49Admin Login and RegistrationNoneTODO3
SCRUM-48List Purchased Tickets - AdminNoneTODO3
SCRUM-46Create Tickets - AdminNoneTODO3

Team Velocity: 0

Sprint Review

ConcludedQuantity
Tasks0
Epics0
Story Points0

Sprint Retrospective

In this sprint, we were unable to complete any of the tasks due to a lack of time to invest in the project. We were working on other projects, and none of the team members could dedicate much time to this project. We tried to do the terraform for deploying the project, but we were unable to complete it. We were also unable to do the daily stand-ups; instead, we organized two short weekly meetings to discuss each team member's progress.

Sprint Burndown Chart

Burndown Chart